Professional installation guide following NHBC guidelines and building regulations for optimal performance of your Anti-Damp Vent system.

Installation Overview

Building Regulations Spacing

  • DPC Level: 1 vent every 900mm (4 bricks)
  • Above Lintels: 1 vent every 450mm (2 bricks)
  • Cavity Trays: 1 vent every 450mm (2 bricks)

Installation Types

  • New Build: Place between bricks during construction
  • Retrofit: Replace existing weep vents or drill new openings

Step-by-Step Installation Guide

New Build Construction

Step 1: Planning Vent Positions

Mark out vent positions according to building regulations:

  • Every 900mm (4 bricks) along the DPC
  • Every 450mm (2 bricks) above lintels and cavity trays
  • Ensure vents align with cavity space

Step 2: Installation During Bricklaying

Simply place Anti-Damp Vents between bricks during construction:

  • Position vent flush with external wall face
  • Ensure full contact with cavity
  • Bed in mortar as normal
  • Check vent is level and secure

Step 3: Enhanced Ventilation (Optional)

For optimal results, install additional vents at ceiling level:

  • Use same spacing as DPC level (900mm)
  • Creates vertical airflow through cavity
  • Use inlet plugs to control airflow direction

Retrofit Installation

Required Tools

  • 10mm masonry drill bit
  • 8mm diameter x 100mm (min) mortar rake
  • Hammer drill
  • Safety equipment (goggles, dust mask, gloves)
  • Spirit level

Step 1: Preparation

Identify existing weep vents or mark new positions:

  • Locate existing weep vents or perpend joints
  • Mark positions following building regulations
  • Check for cables or pipes before drilling
  • Ensure safe access to work area

Step 2: Drilling and Cleaning

Carefully create or clean openings:

  • Drill out perpend joints with 10mm masonry bit
  • Use mortar rake to clean debris from opening
  • Ensure opening reaches cavity (minimum 100mm deep)
  • Take care not to damage DPC, cavity trays, or lintels
  • Clear all dust and debris from opening

Step 3: Vent Installation

Insert and secure Anti-Damp Vents:

  • Push vent fully into cleaned opening
  • Ensure vent sits flush with wall surface
  • Check vent is level using spirit level
  • Apply small amount of sealant if needed for secure fit

Important Safety Considerations

  • Always wear appropriate safety equipment
  • Check for electrical cables and water pipes before drilling
  • Take extreme care not to damage DPC or cavity trays
  • Work from stable platform when installing at height
  • Consider professional installation for complex retrofits

Advanced Installation Techniques

Stack Effect Enhancement

Maximize moisture extraction by creating vertical airflow:

Installation Pattern:

  • 1. Install vents at DPC level (standard spacing)
  • 2. Install matching vents at ceiling level
  • 3. Use inlet plugs on upper vents for extraction
  • 4. Creates natural convection current

Targeting Problem Areas

Additional vents for specific moisture issues:

High-Risk Areas:

  • North-facing walls (reduced drying)
  • Near bathrooms/kitchens
  • Areas with visible damp issues
  • Corners and cold bridges

Installation Tools & Accessories

Essential Tools

  • • 10mm masonry drill bit
  • • 8mm x 100mm mortar rake
  • • Hammer drill
  • • Spirit level

Safety Equipment

  • • Safety goggles
  • • Dust mask
  • • Work gloves
  • • Ear protection

Accessories

  • • Inlet plugs for directional flow
  • • Measuring tape
  • • Chalk line for marking
  • • Vacuum for cleanup

Professional installation tools available in our shop
Visit Shop for Installation Kits →

Need Professional Installation?

Find approved installers in your area or contact us for installation support